Summary:
Explanation:
• This screen user can view summary of the cross project assignments of all resources who are members of selected business for the 6 months period from selected start month and year.
This drop down list holds all businesses list, user is member of.
This grid shows the group wise assignments of resources who are members of selected business from selected start month and year to next 6 months.
• This screen shows total hours of all tasks of the project for each month with a link; on clicking this link a popup will open showing the task details of selected month and project of that resource.
• Links in grid will available if it contains any number, for the zero there will be no link to view details.
• Here clickable total is also available which will display the all task of all project of that particular resource and month.
• Free Time: shows the total hours available as [Total 6 months work hrs. – total assigned hrs.] Calculating work hours of a single month by calculating number of work days in a month.
• In the group summary of all resources, if in particular month task assigned hours becomes more than working hours in a month it will show in red.
Red cells shows resources is over assigned for that month.
This popup screen opens after clicking on link of grid value, which displays the task details of that particular month and project.
• The pop displays complete detail of task, so task start and end date could be expanded on displayed month.
• The light blue rows shows there is no progress in work and Yellow rows show work is in progress or it has been completed.
Data Explanation:
1. Assigned hours distributed from month Feb08 to Aug08, to all three resources Dustin Kassman, Ed Lee and Ken Winston for RM_ Project1.
2. RM_Project2 is only assigned to resource Ed lee in month April08.
3. Total assigned hours for RM_Project1 and month Feb to Aug is same as declared in sample data Assignment. And For RM_Project2 it is also same.
4. For resource 'Dustin Kassman', he has three task (Summary: Widget X, Specification and Implementation) which is started from month feb08.
He is assigned 50% so he will work 4Hrs (50% of 8hr or total working hr in a day) in a day. Now,
• Total work in task 'Summary: Widget X' is 199Hrs (4Feb to 15Apr) and in Feb08 (4Feb to 29Feb, total 20 days to work) it is 20*4 = 80Hrs only.
• Total work in task 'Specification ' is 29Hrs (4Feb to 13Feb) and in Feb08 it is all 29 Hrs.
• Total work in task 'Implementation' is 49Hrs (23Feb to 12Mar) and in Feb (23Feb to 29Feb08, total 5 days to work) it is 5*4 = 20Hrs only.
Therefore in Month Feb08 Resource 'Dustin Kassman' has to work 129Hrs (80Hrs + 29Hrs + 20Hrs) for RM_Project1, which is displaying in Grid for the resource. And if we click on the link 129 we will see task detail of these 3 tasks only.
Similarly if we see it for month march there will be four tasks which are come in March for RM_Project1.
• Total work in task 'Summary: Widget X' is 119Hrs (1Mar08 to 14Apr08, Feb08 task is subtracted) and in Mar08 (1Mar to 31Mar, total 21 days to work) it is 21*4 = 84Hrs only.
• Total work in task 'Concept' is 10Hrs (26Mar08 to 2Apr08) and in Mar08 (26Mar to 31Mar, total 3 days to work) it is 3*4 = 12Hrs which is more than total work so it is 10Hrs only for March month.
• Total work in task 'Implementation' is 29Hrs (1Mar08 to 12Mar08, Feb task is subtracted) and in Mar08 (1Mar08 to 12Mar08, total 8 days to work) it is 8*4 = 32Hrs which is more than total work so it is 29Hrs only for March month.
• Total work in task 'Evaluation' is 22 Hrs (28Mar08 to 14Apr08) and in Mar08 (28Mar to 31Mar, total 2 days to work) it is 2*4 = 8Hrs only.
Therefore in Month March Resource ‘Dustin Kassman’ has to work 131Hrs (84Hrs + 10Hrs + 29Hrs + 8Hrs) for RM_Project1, which is displaying in Grid for the resource. And if we click on the link 131 we will see task detail of these 4 tasks only.
The same calculation procedure is followed for all month and all resources assignments calculation in this report.