Project Summary:
Explanation:
• This screen shows Assignment Summary for all resources who are members of selected business of selected project from the list of all projects which belongs to selected business.
This drop down list holds all businesses list, user is member of.
These are the projects user is members of the Business selected, loaded on change of Business without refreshing the page.
Grid shows single project assignment selected from Project drop down list in hours for every month of 12 months period starting from selected start month year, of all resources who are member of selected business.
• Other projects are all other projects except that selected project assigned to the resource.
• ‘Total’ shows sum of all months assigned hours of all projects of particular resource, it will show in red if the
sum gets more than working hours in a month.
Red cells shows resources is over assigned for that month.
Data Explanation:
1. Assigned hours distributed from month Feb08 to Aug08, to all three resources Dustin Kassman, Ed Lee and Ken Winston for RM_ Project1.
2. RM_Project2 is only assigned to resource Ed lee in month April08.
3. Total assigned hours for RM_Project1 and month Feb to Aug is same as declared in sample data Assignment. And For RM_Project2 it is also same.
4. For resource 'Dustin Kassman', he has three task (Summary: Widget X, Specification and Implementation) which is started from month feb08.
He is assigned 50% so he will work 4Hrs (50% of 8hr or total working hr in a day) in a day. Now,
• Total work in task 'Summary: Widget X' is 199Hrs (4Feb to 15Apr) and in Feb08 (4Feb to 29Feb, total 20 days to work) it is 20*4 = 80Hrs only.
• Total work in task 'Specification ' is 29Hrs (4Feb to 13Feb) and in Feb08 it is all 29 Hrs.
• Total work in task 'Implementation' is 49Hrs (23Feb to 12Mar) and in Feb (23Feb to 29Feb08, total 5 days to work) it is 5*4 = 20Hrs only.
Therefore in Month Feb08 Resource 'Dustin Kassman' has to work 129Hrs (80Hrs + 29Hrs + 20Hrs) for RM_Project1, which is displaying in Grid for the resource.
Similarly if we see it for month march there will be four tasks which are come in March for RM_Project1.
• Total work in task 'Summary: Widget X' is 119Hrs (1Mar08 to 14Apr08, Feb08 task is subtracted) and in Mar08 (1Mar to 31Mar, total 21 days to work) it is 21*4 = 84Hrs only.
• Total work in task 'Concept' is 10Hrs (26Mar08 to 2Apr08) and in Mar08 (26Mar to 31Mar, total 3 days to work) it is 3*4 = 12Hrs which is more than total work so it is 10Hrs only for March month.
• Total work in task 'Implementation' is 29Hrs (1Mar08 to 12Mar08, Feb task is subtracted) and in Mar08 (1Mar08 to 28Mar08, total 8 days to work) it is 8*4 = 32Hrs which is more than total work so it is 29Hrs only for March month.
• Total work in task 'Evaluation' is 22 Hrs (28Mar08 to 14Apr08) and in Mar08 (28Mar to 31Mar, total 2 days to work) it is 2*4 = 8Hrs only.
Therefore in Month March Resource ‘Dustin Kassman’ has to work 131Hrs (84Hrs + 10Hrs + 29Hrs + 8Hrs) for RM_Project1, which is displaying in Grid for the resource.
The same calculation procedure is followed for all month and all resources assignments calculation in this report.